HomeArchitecture/planningNew Brunswick introduces strict criteria for data centre developments

New Brunswick introduces strict criteria for data centre developments

Canadian Design and Construction Report staff writer

The New Brunswick government has released a new data centre development policy establishing strict approval requirements for proposed projects, including protections for electricity ratepayers, environmental considerations and community involvement.

Under the policy, no data centre proposal will receive government approval unless:

  • Ratepayer and electricity system impact: Data centre developments will not be approved unless they provide a net benefit to electricity utilities and their customers and must not compromise system reliability.
  • First Nations and community benefits: Meaningful engagement with communities and First Nations will be required throughout the development process. Commitments made with First Nations and communities should be supported by binding agreements.
  • Water, environmental and community impact: Data centre developments will not be approved unless they are designed to minimize impacts on air, greenhouse gas emissions, water, land, local infrastructure and the environment, while promoting the responsible use of resources.
  • Economic value: Projects must demonstrate the economic benefits they bring to New Brunswick, including new investments, job creation, workforce training, research and innovation, and opportunities for local and First Nations businesses.
  • Project viability and alignment: The provincial government will not approve projects unless they can demonstrate they are technically and financially sound, are compatible with provincial economic, environmental and infrastructure objectives, and align with provincial and national priorities, including data sovereignty.

Post-Secondary Education and Training Minister Jean-Claude D’Amours said the policy outlines the criteria a project must meet to move forward while giving government the tools to say no to any project that is not right for New Brunswick.

“We know New Brunswickers have concerns about data centres, and that is why we have set the bar high,” said D’Amours. “We will say no to projects that don’t meet our requirements, and they won’t be allowed to proceed.”

The government will pursue any legislative and regulatory changes that are needed to implement the policy.

The policy establishes five key areas that will guide government decisions: electricity system impacts, First Nations and community benefits, environmental and infrastructure impacts, economic value, and project viability and alignment with provincial and national priorities.

The policy is intended to give communities a greater role in determining whether proposed developments are appropriate for their area.

The government also intends to introduce amendments to the Electricity Act that would establish a government review and approval process for electricity supply arrangements involving proposed data centres.

The changes would focus on protecting ratepayers and ensuring projects deliver measurable benefits to New Brunswickers.

Large data centre developments also would be required to register for an environmental impact assessment under planned amendments to the Environmental Impact Assessment Regulation of the Clean Environment Act.

Post-Secondary Education and Training Minister Jean-Claude D’Amours said the policy establishes the requirements projects must meet and gives government the authority to reject proposals that do not serve the province’s interests.

“We know New Brunswickers have concerns about data centres, and that is why we have set the bar high,” said D’Amours. “We will say no to projects that don’t meet our requirements, and they won’t be allowed to proceed.”

Energy Minister René Legacy said electricity demand will be a major consideration as the province evaluates proposals.

“Energy demands are always a significant concern, and ensuring New Brunswickers continue to have access to the reliable electricity they depend on in their daily lives remains a top priority for our government,” said Legacy.

The government will pursue any additional legislative and regulatory changes required to implement the policy.

The requirements will apply to all proposed data centre developments in New Brunswick, regardless of their current stage of planning or development. Projects already under consideration will be subject to the same criteria as new proposals.